Bloomfield, Connecticut: Midstate Site Development was the low bidder on these two separate projects slated for the summer of 2009. Both projects had to be started the day after school dismissed for summer break and be totally complete by the start of school in the fall. Midstate hit the job running with multiple crews. We made up to 8 sidewalk concrete pours per day, reclaimed multiple parking lots and main driveways, installed new sewer and water mains, site lighting, and landscaping. The project was done ahead of schedule and made for a smooth transition for teachers and students when they returned.